Free Project Closure and Lessons Learned Learning Path
The handover archive

GOAL
Assemble a closure pack that separates accepted outputs, residual work, operational ownership and evidence-based lessons for the next project.

START
Read workbook.html, inspect case-data.csv, complete the five stage outputs, then the capstone. Use evidence-log.csv to record only actions actually performed.

CASE
Willow Club has delivered a workshop-booking page. The form and export passed acceptance, but a help article is unfinished and an automated reminder was explicitly deferred. Operations starts Monday. A closure meeting must avoid presenting deferred scope as a defect or leaving unfinished agreed work without an owner.

TOOLS
Basic project experience or willingness to use a fictional example. No project-management software is needed.

LOCAL COMMANDS / OPENING
Open workbook.html in a browser; complete the case-specific worksheets in your preferred free editor or on paper.

ASSESSMENT
Score at least 80/100, supply every required artifact, and satisfy the path-specific critical condition. Rework missing evidence before marking complete.
Critical condition: No unresolved baseline item disappears from the closure record and no future benefit is claimed as already realized.

SOURCE COURSES
Project Closure: Free Course — https://wikifree.com/courses/free-onlinepmcourses-project-closure/
Managing Workplace Teams: Free Course — https://wikifree.com/courses/free-management-courses-managing-workplace-teams/

RIGHTS AND SCOPE
Original WikiFree teaching case and exercises. All case data are synthetic. Provider lessons are linked, not redistributed. No certificate, real project delivery or unperformed runtime test is claimed.